Date Progress
June 2019

08 June 2019:

Mighty Earth RRR16 alleged that 115 hectares of forest clearance and an additional 40 hectares of clearance preparation from 17 April – 27 May 2019 in Menthobi Mitra Lestari concession. The report further alleged linkages of Menthobi Mitra Lestari to Bakrie Group.

We reached out to Bakrie Group for clarification regarding the allegations made in Mighty Earth report 16.

PT Bakrie Sumatera Plantations Tbk has informed us that Menthobi Mitra Lestari is not part of the Bakrie Group.
January 2020 Based on Bakrie Group’s statement that Menthobi Mitra Lestari is no longer part of PT Bakrie Sumatera Plantations Tbk or Bakrie Group since 2017, we consider the Mighty Earth RRR 16 closed.